Before the Gulf War,
Iraqi scientists had progressed through several design iterations for a fission
weapon based on an implosion design (one that is much more difficult to develop
than the alternative, gun-type design. Still at the early stages of completing
a design, they had successfully overcome some but certainly not all of the
obstacles to a workable device. Using HEU, a completed device based on the
latest Iraqi design reportedly might have weighed from about a ton to somewhat
more than a ton.
How close Iraq was to completing a bomb is still open
to debate. At the request of the IAEA, a group of nuclear weapon designers from
the United States, Britain, France, and Russia met in April 1992 to assess the
progress of Iraq’s nuclear program prior to the Persian Gulf War, based on
documents that had been obtained through subsequent inspections. These
designers reportedly concluded that bottlenecks in the program could have
delayed completion of a working bomb for at least 3 years, assuming Iraq had
continued its multifaceted strategy and design approach.
However, several experts familiar with the inspections
believe that lraq could also probably have produced a workable device in as
little as 6 to 24 months, had they decided to seize foreign-supplied HEU from
under safeguards and focus their efforts on a crash program to produce a device
in the shortest possible amount of time.
Iraq had a very
well-funded nuclear weapons program aimed at the indigenous development and
exploitation of technologies for the production of weapon-usable nuclear
material and the development and production of nuclear weapons, with a target
date of 1991 for the first weapon. [S/1997/779]
It is reasonable to suppose that the first device, containing indigenously
produced HEU, would not have been available before late 1992. Equally, if it is
accepted that Iraq's strategy was to acquire a small nuclear arsenal before
testing, it is likely that the need to demonstrate a delivery capability would
not have occurred until 1994. [GC 40-13]
The program comprised:
Although Iraq's
nuclear weapons programme plan, established in 1988, had the objective to
produce a small arsenal of weapons - with the first device being produced in
1991 - the three main components of the programme, namely the production of HEU
from domestic sources of uranium, the design and production of a viable device
and the development of a delivery system, had not progressed equally to meet
the planned schedule. [GC 40-13]
Iraq has developed or
otherwise acquired many of the technologies required to produce deliverable
nuclear weapons, but the attempt made by Iraq to assemble a nuclear device by
diverting HEU from their safeguarded research reactor fuel was a clear
indication that their uranium enrichment programme was still far from
production in January 1991.
In April 1991, Iraq’s inventory of safeguarded highly
enriched uranium included fresh unirradiated fuel used for the Soviet IRT 5000
reactor, including 68 fuel assemblies of 80% enrichment with a U235 content of
10.97 kilograms and 10 assemblies of 36% enrichment with a U235 content of 1.27
kilograms. In addition, there was a set of fresh fuel plates for the French
Tammuz-2 reactor with an enrichment of 93% and a total U235 content of 372
grams. Other highly enriched material included 35.58 kilograms of U235 which
had been irradiated but could not be readily used in weapons production since
the fissile material would have been difficult to extract quickly from the
irradiated fuel. However, it was enriched to 93% which gave it high strategic
value. [IAEA April 1992 ]
Iraq had accumulated considerable experience in uranium metallurgy, and in
January 1991 was ready to commence the recovery of the highly enriched uranium
(HEU) from the safeguarded IRT-5000 research reactor fuel. [S/1997/779]
The crash program
which was initiated in the late summer of 1990 had been planned to comprise the
chemical processing of both unirradiated and irradiated research reactor fuel
placed under IAEA safeguards to recover the highly enriched uranium (HEU) from
the fuel; the re-enrichment of part of the HEU through the use of a 50-machine
centrifuge cascade which was to have been specially constructed for the
purpose; the conversion of the HEU chemical compounds to metal. Had the HEU
recovery and enrichment process been successful, it could have resulted in the
availability by the end of 1991 of a quantity of HEU sufficient to manufacture
a single low-yield nuclear device. Also planned were measures such as the
fabrication of the implosion package and the selection and construction of a test
site and studies of a delivery system. Assembly of the device could not have
been possible, according to the estimate of the Iraqis scientists, before the
end of 1992. It is uncertain whether Iraq would have been able to overcome the
considerable technical difficulties involved in this project. The plan could
not be implemented because of the bombing in January 1991 that destroyed the
technical tools at the nuclear research centre at Tuwaitha for processing the
highly enriched uranium (HEU) contained in the safeguarded research reactor
fuel. [GC 40-13]
The Reactor Project -
Project 182 Iraq's
planned nuclear power program originated in 1975 and with international
assistance, had developed from modest plans to acquire a single 600 MWe unit,
to involve the progressive construction of four to six power plants by the year
2010. Although these plans had been further modified in the mid 1980s, no
practical progress had been made in the acquisition of nuclear power plants
other than the identification of four possible sites suitable for the location
of nuclear power plants.
Iraq's feasibility
studies on the underground sitting of reactors and other fuel cycle related
installations, had been aimed exclusively at providing protection from aerial
attack and that the strategy had been abandoned due to its prohibitive cost.
Although it had been managed by the same IAEC department, Project 182, relating
to the construction of a research reactor, had been an entirely separate study.
This project - which foresaw the construction of an indigenous research reactor
to replace the capability that would have been provided by the Osirak (Tamuz-1)
research reactor - had originated in 1984/85 after the breakdown in Iraq's
negotiations with France for the rebuilding of the Osirak reactor. The Project
182 reactor was explained to have been a natural uranium - heavy water type,
similar to the Canadian NRX reactor. When the project had become more defined,
in 1987 and 1988, studies had concentrated on the design of the reactor core.
As this work progressed it was recognized that considerable IAEC and foreign
resources would be needed to bring the project to fruition. In mid-1988, while
still in the study phase, the project was allowed to lapse due to lack of
available resources - a consequence of the higher priority given to the needs
of the EMIS enrichment program. Studies on the indigenous production of heavy
water had not progressed beyond surveys of technical literature and preliminary
laboratory measurements. [GC 40-13]
In addition to extensive development of the
electromagnetic isotope separation technique (EMIS, also called calutrons) and
preliminary work on centrifuge enrichment technology and materials acquisition,
Iraq had also been pursuing chemical enrichment including both the ion-resin
process developed by the Japanese and the liquid-liquid solvent extraction
process developed by the French.
Iraq
made a deliberate effort to make its nuclear program self-sufficient and to
reduce reliance upon foreign suppliers. In 1981 Israeli aircraft destroyed the
Osirak nuclear reactor at Tuwaitha. After the bombing, there was a debate in
Iraq on how to recover. It was then that they decided to reduce their reliance
upon foreign suppliers and attain nuclear self-sufficiency. At that time, Iraq
appears to have made a political decision to send its nuclear program
'underground
The decision to invest billions of dollars in uranium
enrichment through electro-magnetic isotope separation, the so-called calutron
program, is an example of how Iraq went about implementing this policy of
self-sufficiency. The program did not have to depend on sophisticated imports
needed for more modern and efficient methods of uranium enrichment. The Iraqi
calutron program was largely indigenous and was an improvement over the
technology used by the United States in the 1940's. Iraq had been preparing
secretly to operate hundreds of the relatively simple devices.
Enrichment activities included two industrial-scale
facilities for producing highly enriched uranium at Tarmiya andt, using the
electromagnetic isotope separation (EMIS) method. The Ash Sharka / Al-Sharqat
facility, located over 300 kilometers north of Baghdad, was identical to a
declared enrichment plant at Tarmiyah. The second facility was not completed.
Iraq's facilities were comparable in size to the electromagnetic isotope
separation of the Manhattan Project, which developed the US atomic weapons in
the 1940s, representing a four-to eight-billion-dollar investment on the Iraqis'
part. The calutron technology is not obsolete, though it is expensive -- this
technique has not been used for 45 years because it is not economic. Once the
plants at Al Sharqat and Tarmiyah went into operation, Iraq would have been
able to produce enough enriched uranium for one bomb a year from each plant. No
industrial production had started at the two plants, but both would have been
operational in 1992 or 1993.
The leader of the Iraqi enrichment program, Dr.
Jaffar, initially claimed that the primary aim of the program was to develop a
technological and industrial infrastructure, and that enriched uranium was
needed for the research reactors and for a future nuclear power program. But to
produce one gram of uranium enriched at 3.5 percent (which is the type of
uranium needed by a nuclear power plant) through the electromagnetic approach
would involve spending five times more energy than the energy produced by the
reactor. The combination in the Iraqi EMIS program of high capacity/modest
separation and low capacity/high separation would be particularly useful if the
goal was to produce highly enriched uranium. [DGSP 1991-3]
Although Iraq was at, or close to, the threshold of success in its endeavor to
produce highly enriched uranium through the electro-magnetic isotope separation
(EMIS) process, there is no indication that Iraq has produced more than a few
grams of weapon-usable nuclear material nor any indication that Iraq has otherwise
acquired such material. [S/1998/694]
Iraq claimed that only about half a kilogram of uranium at an average
enrichment level of 4% had been produced.
Iraq has claimed that
the primary objective of the gas centrifuge uranium enrichment had been to
exploit the tested, prototype single cylinder model, and that all resources had
been directed toward this objective. The small amount of work that had been done
with a view to exploiting the design drawings of super-critical two-cylinder
and multi-cylinder centrifuge designs were asserted to have been a "spare
time" study, which had achieved little of consequence. It was explained
that this study had been biased towards the more complex, multi-cylinder,
design simply because there were more design details available for that
machine. Iraq has claimed that, although it would have eventually sought to
exploit higher efficiency centrifuge designs, the primary goal had been the
large-scale exploitation of the single cylinder machine, which it considered to
be a proven design. The modifications which had been made to buildings at Al
Furat and EDC Rashdiya were stated to be very much forward-looking and should
not be taken to imply that hopes of early exploitation of multi-cylinder
centrifuge designs had been seriously entertained. [S/1997/779]
No evidence had been
found by the IAEA as of 1996 of practical progress towards the establishment of
the 50-machine centrifuge enrichment cascade, although it appears that external
assistance was to have been relied upon for the procurement and production of
the carbon fibre cylinders and other components of the centrifuge rotors. [GC 40-13]
Iraq has claimed that the Petrochemical-3 project
(PC-3) had adopted a policy of avoiding foreign assistance, believing that the
risk of exposure (e.g., through "sting" operations) far outweighed
the likely technical benefits. [S/1997/779]
But many drawings and specifications relating to centrifuge machines had been
provided through foreign assistance, some of which concerned advanced technology,
multi-cylinder machines. Iraq had planned to build a third centrifuge facility
at a location in south Taji which would have accommodated cascade halls of up
to 1,000 machines and, which according to Iraq, would have been the site of a
future commercial scale UF6 production facility. Iraq's rapidly developing
program for the design, development, manufacture and operation of gas
centrifuge machines was not, according to Iraq, matched by a similar high
priority plan for the secure supply of production-scale amounts of UF6 - the
basic feed material. Iraq has declared its laboratory-scale UF6 production
capacity to have been more than adequate to support the ongoing development
activities in 1990 and considered that there was no urgency to provide for large-scale
production. [S/1997/779]
Iraq imported large
quantities of raw materials and components required for the manufacture of
centrifuges to produce enriched uranium, sufficient to produce a few thousand
centrifuges. The main items included: special aluminum alloy extrusions for the
manufacture of centrifuge vacuum housings; ferrite magnets and other components
used in the stator of centrifuge motors; and special equipment needed to fix
the stator components in place. Iraq also obtained: 100 tons of special high
strength steel (maraging steel) for centrifuge rotors and rotor fittings; and
several thousand aluminum forgings for vacuum housing flanges. The quantities
involved would have sufficed for the manufacture of several thousand
centrifuges. Iraq's centrifuge enrichment program had not progressed to a point
where they could have started a sizeable production of centrifuges, although
given time, they would have been successful. The program had developed to a
point, however, where the material necessary for certain key components had
been identified. This enabled the procurement of materials as opportunities
became available even though the centrifuge design had not been completely
finalized nor the manufacturing process fully implemented. The operation of a
production scale uranium-enrichment centrifuge cascade, given the state of
Iraqi centrifuge technology when work stopped, would have required the foreign
procurement of large numbers of finished components. Iraq was constructing a
facility deemed by experts as being capable of producing a few thousand
centrifuge machines a year. [IAEA April 1992 ]
Iraq invested
significant resources into uranium enrichment through laser isotope separation
(LIS) involving both molecular (MLIS) and atomic vapor (AVLIS) technologies,
including a number of activities with respect to laser component manufacture,
particularly CO2 lasers and the manufacture of components for use in
laser-related experimentation. The Laser Section within the Physics Department
of the Iraqi Atomic Energy Commission [IAEC] at Tuwaitha received an objective
in 1981 from the IAEC to work in Laser Isotope Separation. It started in two
lines; one which was looking after the molecular and the other the atomic vapor
direction. When the achievements of the Laser Section were evaluated in 1987 it
was decided that the project should be downgraded to a "watching
brief" and that a number of key personnel should be transferred to other
projects, notably electromagnetic isotope separation [EMIS]. This loosely
coordinated and largely empirical approach to LIS had apparently not reached
the point of an integrated experiment that achieved any isotopic separation of
either elemental uranium or UF6 or that they had developed even the most
rudimentary capabilities in either AVLIS or MLIS technologies. Export controls
and voluntary refusals on the part of several equipment suppliers had severely
hampered the Iraqi LIS activities by preventing the procurement from abroad of
critical pieces of equipment, most notably copper vapor laser systems. [GC 39-10]
The opinion of IAEA experts was that Iraq's explanation of its LIS activities
was plausible, but surprise was expressed that Iraq had not undertaken the
relatively simple step of vaporizing uranium metal. [S/1997/779]
Iraq made some
progress in chemical (solvent extraction) and ion-exchange methods for the
enrichment of uranium, before the outbreak of the Gulf war. All of the
activities carried out had taken place at the Nuclear Research Centre,
Tuwaitha, except for the production of tri-butyl phosphate which, together with
some theoretical work on crown ethers, had been done at Muthanna. The
motivation to develop the chemical enrichment process had been Iraq's wish to enhance
the capability of the EMIS (Electromagnetic isotope separation) process by
feeding low enriched instead of natural uranium. Iraq appears to have done only
limited, basic laboratory-scale work in solvent extraction for uranium
enrichment. However, Iraq could have addressed the practical problems that
would have arisen during scaling-up. At the time it had been in the process of
procuring components for a pilot plant to produce four tons per year of 1 to
1.2 % enriched uranium. Concerning ion exchange enrichment technology, the
approach was promising, but that a lot of work was needed, as experience with
it was limited in Iraq. The results of laboratory scale experiments, using
indigenously produced ion exchange resins, were stated to have been modest and
a similar project for a pilot plant to produce four tones per year of up to 3%
enriched uranium had not gone beyond the preliminary assessment of equipment
and material requirements. The most promising project, though still at the
conceptual design stage in late 1990, combined both enrichment methods in an
hybrid process having a solvent extraction first stage and an ion exchange
output stage, in order to produce up to 5 tones per year of 4 to 8% enriched
uranium. [GC 40-13]
The First Group of
IAEC Department 3000 continued its work in the production of diffusion barriers
and compressors, which are key components of gaseous diffusion enrichment
technology, after its relocation from Tuwaitha to the Engineering Design Centre
(Rashdiya). Some significant achievements had been attained in the development
of anodized aluminums barriers. It had been able to demonstrate the corrosion
resistance of the barrier material to UF6 and had achieved measurable uranium
isotopic separation. However, this activity, carried out in 1989, had not
progressed beyond the qualification of a single type of barrier. In parallel to
barrier studies, attempts to reverse-engineer compressors had been made, in
co-operation with Iraq's Specialized Institute for Engineering Industries.
However, these attempts had not been successful. All activities related to
gaseous diffusion had been stopped in 1989 and priority given to exploiting the
progress made in as centrifuge enrichment technology. [GC 40-13]
Activities carried out
at first at Tuwaitha and later at Al Atheer had been aimed at the production of
a nuclear device, and not only to the definition of what was required to
produce it. The involvement of the Al Qa Qaa State Establishment in support of
the development of the implosion package began in 1987. [GC 40-13]
Iraq had made
significant progress in weaponization technologies before April 1991. [S/1998/694]
The Iraqis possessed flash x-ray photography equipment and high-speed streak cameras
-- both useful in the R&D phase for studying the timing and compression
achieved by a nuclear implosion design.
A significant decision
been taken regarding the dimensions of the explosive lens of choice at a
meeting of 12 January 1991. This decision strongly indicated that similar
decisions had been taken regarding the design of the weapon internals. While
the size of the explosive lenses had been fixed at the meeting of 12 January
1991, Iraq asserts that the decision had been reached empirically and had been
most strongly influenced by the restriction on the external diameter of the
nuclear weapon imposed by the most appropriate missile delivery vehicle
available at that time. Iraqi contends that no decision had been made with
respect to the design of the weapon internals and, that no practical
experiments had been made to support any particular design concept. [S/1998/38]
Iraq maintains that,
despite the increased urgency imposed by the so-called 'crash program', it had
not yet identified design options beyond those preliminary concepts described
in the last version of the PC-3 Group Four report entitled "Basic design
report of the implosion device", dated 14 July 1990. It further maintains
that no experimental program had been established through which to validate
possible options identified by computation. [S/1998/38]
Iraq's nuclear weapons
program, as planned in 1988, foresaw the production of the first weapon in
1991. However, the nuclear weapon in the mid-1988 conceptual design was deemed
to be far too heavy to be delivered by missile. Consequently the PC-3 Fourth
Group (Weapon development) had been advised to modify the design "with a
view to reducing the total weight of the projectile (payload) to about one ton
or less". It appears that three delivery vehicle options were pursued: [GC 40-13]
Although discounted as
impracticable by Iraqis, it seems reasonable to suppose that the shorter term -
crash program - option was the attempt, stated to have been initiated in
August/September 1990, to produce a derivative of the Al Hussein/Al Abbas
missile designed to deliver a warhead of one tone up to 650 km and to
accommodate a nuclear package of 80 cm diameter.